RTS Link viaduct construction across the Straits of Johor
Construction of the Johor Bahru-Singapore RTS Link on Sept. 26, 2024. File photo; passenger services are targeted for February 2027, subject to safety certification and approvals. Source: https://commons.wikimedia.org/wiki/File:Johor_Bahru–Singapore_Rapid_Transit_System_construction_site_on_2024-09-26_1.jpg License: https://creativecommons.org/publicdomain/zero/1.0/ Resized for publication. Renek78 / Wikimedia Commons / CC0 1.0

The Johor Bahru-Singapore Rapid Transit System Link is targeting passenger services in February 2027, with Malaysia's transport minister saying Oct. 8 that extra time would allow safety assessments and regulatory approvals before the cross-border railway opens.

The timetable remains conditional. RTS Operations must secure an independent safety certificate and final permission from authorities in both countries, according to the joint statement issued Oct. 2 by Malaysia's Ministry of Transport and Singapore's Land Transport Authority.

Transport Minister Anthony Loke said the intended opening was around mid-February, but an exact date could be confirmed only after the necessary approvals, CNA reported. He made the remarks at the launch of expanded BAS.MY bus services at JB Sentral.

Testing Comes Before Passenger Operations

Infrastructure on both sides of the border is substantially complete, the two authorities said. RTS Operations expects to finish final system testing and trial runs by Dec. 31, 2026. Independent safety certification would follow, before regulators review the findings and decide whether passenger operations can begin.

That sequence distinguishes the completion of construction from the opening of a public service. A station or bridge can be physically ready while the operator still has to demonstrate that the integrated railway is safe to run.

Loke said an earlier start in January might be technically possible, but the government wanted additional time to complete the processes properly. The announcement therefore gives commuters a planning window rather than a confirmed first day on which they can board.

The latest joint announcement supersedes older project material that still refers to an end-2026 service target. It does not provide an unconditional guarantee that all approval requirements will be completed by February.

What the Link Is Designed to Offer

The LTA's project description sets out a four-kilometer route between Bukit Chagar in Johor Bahru and Woodlands North in Singapore. The train journey is expected to take about five minutes, with peak capacity of up to 10,000 passengers an hour in each direction.

Those figures describe the railway's design. The five-minute ride is not a promise about a passenger's full trip from home to work, which also involves reaching the station and completing border formalities.

Both countries' customs, immigration and quarantine facilities will be co-located at the departure point. Travellers will clear the two authorities before boarding and will not repeat immigration clearance at the destination. Woodlands North will connect with Singapore's Thomson-East Coast Line.

RTS Operations is a joint venture between Malaysia's Prasarana and Singapore's SMRT. The project is intended to improve the connection across the Straits of Johor and ease pressure on the Causeway.

Bus Connections Will Shape the Arrival Experience

Johor Bahru is also preparing onward transport. CNA reported that about 20 additional bus services were planned to connect RTS passengers with malls including Mid Valley Southkey, Toppen Tebrau and Paradigm Mall, and residential areas such as Kota Masai, Permas Jaya and Taman Pulai Mutiara.

The proposed services would run at intervals of 15 to 30 minutes and offer at least 70 trips daily, Loke said. These are planned connections, and the report does not establish a start date for every route.

Safety approval is a separate requirement from these transport improvements. The LTA's general rail safety framework requires developers to demonstrate safe design and construction, and operators to show that they can operate and maintain a system safely.

For prospective passengers, the remaining milestones are the conclusion of trials, independent certification and permission from both regulators. Until those steps are complete, February remains the target for service rather than a fixed opening date.