Malaysia's communications regulator has selected a Telekom Malaysia subsidiary to install a new submarine cable network linking Peninsular Malaysia, Sabah and Sarawak, with an approved cost ceiling of RM2.7 billion. Telekom Malaysia disclosed the designation Tuesday and said the starting date and delivery timetable depend on its formal acceptance of the terms.

The company's Bursa Malaysia disclosure names TM Technology Services, a wholly owned subsidiary, as the designated universal service provider for the first part of the Sambungan Kabel Dasar Laut MADANI project, known as SALAM. The notification sets Dec. 15 as the scheduled start and calls for phased completion by the first quarter of 2030. TM said it was reviewing the notification and would disclose further material developments.

The project covers four cable segments, including the equipment and infrastructure required to operate them. The subsidiary's scope includes designing the system, carrying out marine works, installing land cables and integrating the transmission and network management equipment. The work also includes testing and commissioning. For customers, those later stages matter because a cable laid offshore still needs working connections to land networks before it can carry commercial traffic.

The proposal is the first part of SALAM, as identified in the filing. For the equipment supplier and engineering teams, completing one segment can involve distinct marine and land work from another segment. A phased end date makes the acceptance of individual systems and subsequent announcements more informative than a single project value for tracking delivery.

More Routes Between the Peninsula and Borneo

The Malaysian Communications and Multimedia Commission said the plan calls for approximately 5,500 kilometers of cable and 10 new landing stations, according to Bernama's account of the regulator's statement. Funding is to come from the Universal Service Provision fund. The stations are the points where the offshore segments connect with infrastructure on land. A network with multiple landing points can give operators more options for routing traffic between regions, depending on the design and the land connections serving each point.

The regional links are the part of the approval with the clearest relevance to Sabah and Sarawak. Schools, hospitals and firms use services that depend on moving large volumes of data across networks. Extra routes can help operators keep services functioning when another path is unavailable. A subsea system addresses the trunk connection. The quality of an internet connection at a home, office or school also depends on the local access network and the plan a customer buys.

The regulator told Bernama that utilization on the existing subsea network, which has been operating since 2017, had reached about 85% of capacity. That figure is for the network described in the regulator's statement. For telecommunications operators, it helps explain why additional trunk capacity is under consideration even if an individual customer has yet to see a local network upgrade.

What the Approval Establishes

RM2.7 billion is the maximum project cost approved in the notification. The filing ties both implementation and financial impact to acceptance and fulfilment of conditions. It provides a timetable for phased construction and completion while leaving the details of when individual segments will enter service for later disclosures.

The designation uses a universal service mechanism for shared network infrastructure. For TM investors that makes the terms of implementation, funding and timing important to the project's eventual financial impact. For businesses and households in East Malaysia, the practical milestones are the locations and activation dates of the landing stations, the links to local networks and the capacity operators make available. The immediate item to watch is TM's decision on the notification, followed by any confirmation of the proposed December start.