Shell Starts Gas Production at Rosmari-Marjoram Off Sarawak
The deep-water development connects new offshore supply to Bintulu's LNG industry through a 207-kilometer pipeline and a dedicated processing plant.

Shell has started producing gas from the Rosmari and Marjoram fields off Sarawak, bringing a major development into operation four years after its investment approval and adding supply for the Petronas LNG complex in Bintulu.
Sarawak Shell Berhad announced the start-up Tuesday. The fields lie about 220 kilometers offshore, and their gas travels to a new onshore plant for processing before entering the LNG complex, Shell said in its production announcement.
The project is expected to produce 800 million standard cubic feet a day, according to Shell's project account. That is the development's expected production capability. The company did not announce that it had already sustained that rate or specify a date for reaching it.
Processing is a central part of the development
Rosmari and Marjoram were discovered in 2014 in waters around 800 meters deep. Their gas contains hydrogen sulfide, requiring treatment before it is delivered onward. The project includes an unmanned wellhead platform, subsea connections, the long pipeline to shore and the Bintulu processing plant.
The treatment requirement helps explain why first gas is more than the opening of an offshore well. The onshore plant provides the link between the raw gas stream and an established LNG production center that serves customers beyond Malaysia.
Shell's description of its sour-gas operations identifies gas treatment and sulfur recovery among the technologies involved in preparing such resources for use. The company describes the pipeline as one of its longest for sour wet gas.
For Sarawak, the development brings another producing asset into an existing gas industry rather than creating an isolated export operation. Shell said it has produced offshore gas in Malaysia since 1982 and also holds interests in fields including Timi and Gorek.
Solar power offshore, hydropower onshore
The offshore platform uses solar panels and batteries when operating without a permanent crew. Diesel generators provide backup and support activities that require more electricity when personnel are present.
The onshore plant draws electricity from Sarawak's predominantly hydropower-based grid. Shell supplements that supply with renewable energy certificates to match the equivalent of all its power consumption with renewable sources.
These arrangements concern the electricity used to operate the facilities. They should be distinguished from the emissions associated with producing, transporting and eventually burning the gas itself. The start-up announcement did not provide a full life-cycle emissions comparison for the project.
Shell says 240 solar panels provide most of the platform's electricity, with batteries designed to support up to three days of operation. Designing for a normally unmanned facility reduces the need to maintain the full set of services used when crews are on board.
The 207-kilometer pipeline and onshore treatment facility also show the difference between distance from shore and the length of a dedicated transport connection. The fields' approximate offshore location describes where the resource lies; the pipeline is one component of the engineered route carrying it into the processing system.
For customers, that processing and transport chain is what converts a deep-water discovery into usable supply. The project's value to the LNG complex depends on the whole chain operating, rather than the offshore platform in isolation.
From construction to output
Shell approved the investment in September 2022. Its 2023 onshore construction announcement had targeted production in 2026, placing Tuesday's announcement within that previously stated year.
Sarawak Shell Berhad operates the development with a 71% interest. The other partners are Petronas Carigali, INPEX Malaysia E&P 2E and SEARAH Malaysia, according to the latest announcement. The current ownership description is the relevant one for the start-up, rather than the original investment-stage shareholding.
The next operating measure will be actual production as the facilities increase output. First gas establishes that the development has moved beyond construction into operation; sustained supply will determine how much it contributes to the Bintulu complex and the wider regional LNG market.