Solar panels in Bukit Merah, Malaysia
Solar panels in Bukit Merah, Malaysia, on Feb. 25, 2023. File photo of a separate site, not a Samaiden-Parkland project. Source: https://commons.wikimedia.org/wiki/File:Bukit_Merah_solar_panel_(230225)_01.jpg | License: https://creativecommons.org/licenses/by-sa/4.0/ *angys* / Wikimedia Commons / CC BY-SA 4.0

Samaiden Group and a renewable energy venture backed by Parkland have agreed to explore projects with up to 1,000 megawatts of combined generating capacity in Peninsular Malaysia. The agreement, announced Nov. 16, gives them a framework for pursuing projects that could sell renewable power to corporate customers through the grid.

The companies' announcement identified the parties as Samaiden Sdn Bhd, a wholly owned subsidiary of the listed company, and Parkland Renewable Energy. Parkland Berhad owns 60% of the venture, with a subsidiary of Hong Kong-listed Xinyi Energy Holdings holding the other 40%. The partners said they could develop projects at multiple sites or in phases, subject to feasibility, regulatory approvals and demand from suitable corporate buyers.

The 1,000-megawatt figure is an upper limit on the capacity the partners intend to explore, expressed in alternating current. It is a measure of power capacity, not a forecast of how many units of electricity the projects will deliver over a year. Neither company named a site or customer in the announcement, and the memorandum did not say how much of the capacity would be pursued first.

Companies could buy power through the grid

The proposal comes under Malaysia's Corporate Renewable Energy Supply Scheme, or CRESS. Under the scheme, a qualifying corporate consumer can arrange to buy renewable power from a developer using the electricity grid to carry the supply. That gives a factory or other eligible business a way to contract for generation at a separate site, rather than being limited to what can be installed at its own premises.

The Energy Commission publishes the scheme's guidelines, including information about the charge associated with using the network. That charge is a separate element from the price negotiated for energy. A purchaser also needs to know how much power a developer can deliver and when. Even projects with similar peak generating capacity can produce different amounts of electricity across a day or a year depending on their technology, location and operating conditions.

The commission and the Ministry of Energy Transition and Water Transformation briefed companies on a CRESS acceleration package in October. Samaiden's announcement provides one indication that developers are examining larger project portfolios under the scheme, although the size of the memorandum alone does not indicate how much new generation will actually reach the grid.

The memorandum runs for 12 months unless extended in writing, and either side can terminate it on 30 days' written notice. It does not commit either party to finance projects or acquire land. Those limits make the figure a potential development pipeline rather than an investment already approved for construction.

From memorandum to power purchase

Samaiden's businesses include engineering, procurement, construction and commissioning of solar photovoltaic systems and power plants, as well as operation and maintenance. Its experience in developing and building projects is different from the decisions needed for this particular portfolio. A proposed site still has to be assessed for suitability and a path to grid access, and the companies have said they need buyers for the output.

The Energy Commission's rules also mean that buying power from a generator through CRESS uses an existing network, rather than a dedicated line from a new plant to each buyer. Which sites are feasible will depend partly on where facilities can connect. For prospective customers weighing offers, connection and delivery dates matter alongside the contracted price and capacity.

The next disclosures that would establish progress include named project locations, confirmed capacities, approvals and agreements with buyers. That would let corporate customers and investors distinguish a potential portfolio spread across Peninsular Malaysia from developments with a timetable and contracted revenue.