Malaysia Approves RM19.05 Billion Sukuk Program for the East Coast Rail Link
The fifth financing program comes as the government reports the line from Kota Bharu to Gombak is 98.5% complete. A separate stretch will take it farther west to Port Klang.

Malaysia has approved a RM19.05 billion sukuk program for the East Coast Rail Link, the railway being built to connect the east coast of Peninsular Malaysia with the Klang Valley and Port Klang. The approval covers Malaysia Rail Link's fifth sukuk program and comes as work on the first stretch, from Kota Bharu to Gombak, moves closer to completion.
Finance Minister II Amir Hamzah Azizan announced the approval Monday at the Gombak Integrated Terminal, where Malaysia Rail Link and CIMB Group Holdings also presented a tokenized sukuk initiative, Bernama reported. The RM19.05 billion is the size of the approved program. The announcement did not say that securities worth the full amount had been sold at the event or give a schedule for all of the issues.
Amir Hamzah said securities issued under the program would be structured as sukuk linked to the United Nations Sustainable Development Goals, continuing an approach used in the previous two programs. Sukuk are securities structured to comply with Islamic finance principles. The financing program is distinct from any decision on ticket prices, freight rates or timetables for the railway's first services.
Two sources of financing
The minister cited RM52.43 billion for the project's construction. The Transport Ministry's Nov. 16 parliamentary explanation separately identified that amount as construction spending for the 665-kilometer route, distinguishing it from other cost components such as land acquisition and interest during construction. He said it included a RM37.40 billion term loan from the Export-Import Bank of China at 3.25%, with local financial institutions involved in financing the remainder through sukuk. The loan and the approved ceiling for the latest sukuk program describe different parts of the financing structure. The announcement did not provide a breakdown that would allow the program's headline amount to be counted as new spending on top of the construction cost.
The Malaysian Investment Development Authority identifies Malaysia Rail Link, a company wholly owned by the Minister of Finance Incorporated, as the owner of the project. China Communications Construction Company is responsible for the engineering, procurement, construction and commissioning work. When completed, the route is intended to carry both passengers and freight, linking Kelantan, Terengganu and Pahang with the west coast.
Amir Hamzah said construction between Kota Bharu and Gombak had reached 98.5% completion as of October. That percentage refers to the initial alignment and does not cover the entire 665-kilometer project. The Gombak terminal, on the edge of the Klang Valley, will provide an initial western endpoint; the connection to Port Klang is a distinct stage with implications for freight operators.
In its parliamentary explanation, the ministry said repayment would follow the agreed financing terms and schedules and would not depend entirely on operating revenue. It said passenger, freight and commercial income would support operation and maintenance. That distinction matters when assessing the railway's finances: a service generating revenue does not, by itself, establish that all development financing can be repaid from those receipts.
The next milestones are on the railway
Malaysia Rail Link previously highlighted the Genting Tunnel as one of the major engineering works on the route. Bore completion on that section marked the end of a major excavation task, but the date a railway can carry passengers depends on work after excavation, including fitting out the route, testing systems and preparing operating staff and stations.
At Monday's event, the minister cited Dec. 12 as the target for the start of commercial operations on the first alignment. Separately, MRL's Nov. 7 handover announcement, reported by Bernama, said the contractor had handed over the 523-kilometer Kota Bharu–Gombak section and trial operations had begun. The trials were scheduled to continue through Dec. 2 under ECRL Operation Sdn Bhd, a 50:50 venture between MRL and the construction company.
The handover and trial program are later milestones than the October construction percentage cited in the financing announcement. They concern the initial operating section, while the full project extends to Port Klang. The sukuk announcement did not provide passenger fares, a timetable or a ticket-purchase link. Travelers planning to use the line should check the operator's service information, while freight businesses need to distinguish the initial alignment from the later port connection.