The Philippine International Convention Center in Pasay, Metro Manila, in a 2021 file photo. Source: https://commons.wikimedia.org/wiki/File:Philippine_International_Convention_Center_interior.jpg | License: https://creativecommons.org/publicdomain/zero/1.0/ Patrick Kasingsing / Brutalist Pilipinas / Wikimedia Commons / CC0 1.0

ASEAN completed the signing of an enhanced regional power grid agreement in Manila on Sunday, extending a framework for electricity trade across Southeast Asia. For Malaysia, the development builds on an operating model in which electricity can be sold from one country to another and carried through the networks of countries in between.

The ASEAN Secretariat's announcement said all member states had signed the enhanced memorandum of understanding. Officials have described the agreement as a basis for increasing cross-border connectivity and multilateral power trade. The signing gives governments a shared framework, while the development of physical links and the terms of individual transactions continue through separate projects and agreements.

That practical work was already underway in April, when the ASEAN Centre for Energy convened regional task forces in Jakarta to consider how to implement the enhanced memorandum. A regional grid depends on technical coordination because a trade can involve the generator, the buyer and one or more grid operators that move the electricity between them.

The Malaysia–Singapore leg is an example of a bilateral connection serving a wider market. An agreement to transport electricity across more than one country can use existing equipment where available. Expansion beyond those limits would require decisions about where extra transmission is needed and who would finance construction and maintenance.

Malaysia's Role in an Existing Route

In January, Tenaga Nasional Berhad and its Lao and Thai counterparts signed a two-year agreement facilitating supply of up to 100 megawatts of renewable electricity from Laos to Singapore. Thailand and Malaysia carry that power across their networks using existing interconnections. Carrying power across an intermediary network for a transaction between other parties is known as wheeling.

The agreement forms part of the second phase of the Laos, Thailand, Malaysia and Singapore Power Integration Project. TNB said the second phase raised overall trading capacity from 100 MW to up to 200 MW, including additional power supplied from Malaysia to Singapore. That figure refers to the maximum capacity under the project. The amount of electricity actually purchased over a particular period depends on the volume and duration of supply.

Malaysia can therefore play two roles across the project. Its network can carry electricity generated elsewhere, and Malaysia can also supply electricity to a buyer in Singapore. Each role brings different arrangements, including how to compensate a network for moving power and how to manage the available capacity of an interconnection.

An interconnector has an operating limit, which makes scheduling important. A utility moving electricity on behalf of another company must account for the capacity already needed on the same equipment. The trial route offers a reference for those arrangements as other ASEAN countries consider links with different generation mixes and distances.

Turning the Framework Into Trade

ASEAN's original regional grid memorandum dates to 2007. The latest signing comes after years of work on projects involving smaller groups of countries. Interconnections can give system operators an additional option when generation or demand changes, provided that the necessary capacity is available and counterparties have workable arrangements.

For Malaysia, implementation can be tracked through published transmission projects and contracts, and through evidence that more electricity is being exchanged. An agreement among governments establishes a basis for that work. Consumers and businesses will see its practical significance through what local utilities ultimately buy, sell or carry, and through the investments needed to support those transactions. Changes in electricity bills would depend on domestic tariff arrangements as well as how the cross-border projects are financed and used.